Introduction |
The Hokkaido Shinkansen is being developed in accordance
with the Nationwide Shinkansen Railway Development Act and
will have some 360 km of tracks from Shin Aomori Station (the
new terminus of the Tohoku Shinkansen since 4 December
2010) to Sapporo through Hakodate, Yakumo, Oshamambe,
Kutchan, and Otaru. It will also incorporate a line between Sapporo and Asahikawa, and a line from Oshamambe through the vicinity of Muroran as a southern route.
The Japan Railway Construction, Transport and
Technology Agency (JRTT) applied for approval of the first
149 km of line between Shin Aomori and Shin-Hakodate
in April 2005 and construction started subsequently with
completion scheduled for fiscal 2015. Along with the Shin
Aomori to Shin-Hakodate (provisional name) approval, JRTT
also applied for development of about 211 km of line between
Shin-Hakodate and Sapporo including Shin Aomori Station
to Sapporo Station, but some sections (where construction
had not started) are not approved yet.
Although part of the broad master plan for the Hokkaido
Shinkansen, some sections between Sapporo and
Asahikawa and the southern route (Oshamambe through Muroran to Sapporo) have not yet materialized. |
Figure 1: Shinkansen Railway Network (Master Plan/ Development Plan)
Figure 2: Hokkaido Shinkansen Map (Development Plan)
Table 1: Events Leading to Hokkaido Shinkansen
Figure 3: Procedures for Shinkansen Line Projects |
Background to Hokkaido Shinkansen Development Plan |
In March 1967, the Sato Cabinet approved an economic
and social development plan that included a shinkansen
construction initiative, marking the de facto start of the
current projected shinkansen lines. Two years later in May
1969, the Cabinet approved the new Comprehensive
National Development Plan forming the foundation of the
current master plan. The Nationwide Shinkansen Railway
Development Act was promulgated in May 1970 and came
into force in June 1970, finally putting laws for shinkansen
development in place. Based on this law, shinkansen
development followed seven stages: (1) decision on master
plan; (2) instruction for surveys; (3) decision on development
plan; (4) instruction for construction under development
plan; (5) approval of construction implementation plan; (6) start of construction; and (7) completion.
In January 1971, the master plans for the Tohoku (Tokyo–Morioka), Joetsu (Tokyo–Niigata), and Narita (Tokyo–Narita) shinkansen were settled on, excluding the Hokkaido
Shinkansen. In April 1971, the master plan was modified
to include the Tsugaru-Kaikyo Line as a construction line,
and the Ministry of Transport (MOT) notified the Japan
Railway Construction Public Corporation (JRCC, now JRTT)
to consider planning for future passage of shinkansen. As a
result, the double track through the Seikan Tunnel was built
to shinkansen specification and the grade was lowered from
20‰ to 12‰, so that speed restrictions would not apply. In
September 1971, JRCC applied to the MOT for approval of
construction (roadbed) between Hamana and Imabetsu in
Aomori Prefecture and Yunosato and Shiriuchi in Hokkaido (Seikan Tunnel) for the Tsugaru-Kaikyo Line. It can be said that the approval in the same month marks the de facto start of construction on the Hokkaido Shinkansen.
In June 1972, the Tohoku Shinkansen terminus was
changed from Morioka to Aomori, and the master plans for
the Hokkaido (Aomori–Sapporo), Hokuriku (Tokyo–Osaka),
and Kyushu (Fukuoka–Kagoshima) shinkansen were added.
At the same time, the MOT issued survey instructions.
The Hokkaido Shinkansen development plan was decided in November 1973 along with plans for the Tohoku,
Hokuriku, and Kyushu shinkansen; the MOT instructed JRCC to start construction.
In November 1973, the Hokkaido Shinkansen terminus
was changed from Sapporo to Asahikawa and a southern
route was announced to run from Oshamambe through
Muroran to Sapporo. These development and master plans are still the active plans today. |
Road To Start of Construction |
Although the Hokkaido Shinkansen (Aomori–Sapporo)
development plan was approved in November 1973, the
road to the start of construction has been long. The 1973
floating exchange rate for the yen resulted in a stronger
yen followed by the oil shocks of 1973 and 1979 and led
to a worsening of Japan’s financial situation. Administrative
reforms, the 1987 JNR privatization and division, and
other tight circumstances delayed funding for shinkansen
construction. Finally, in 1982, the Cabinet decided to delay
the projected shinkansen lines based on a report submitted
by the Second Provisional Commission on Administrative Reform, putting the Hokkaido Shinkansen on hold. However, later talks by the government and ruling parties in August 1988 led to a study on the construction order of priority and the overall plan was maintained. The top priority was the Hokuriku Shinkansen (Takasaki–Karuizawa) and a decision on the section between Karuizawa and Nagano was to be made within 3 years taking into account the issue of Nagano as the venue for the 1998 Winter Olympics. The start of construction between Karuizawa and Nagano was decided in February 1990 and the Hokuriku Shinkansen (Takasaki–Nagano) opened in October 1997 as the first of the planned shinkansen lines.
A 1994 revision of the projected shinkansen lines
decided by talks between the ministries of Home Affairs,
Finance, and Transport promoted route surveying for the
Hokkaido Shinkansen, 8.5 years after studies on the Hokuriku
Shinkansen between Takasaki and Karuizawa had started.
In January 1998, the Government New Shinkansen Line
Examination Commission decided to announce the locations
of stations and routes between Shin Aomori and Sapporo
and to start environmental assessments. An overview of
routes and stations was announced in February 1998 to allow
environmental assessments to start, and the government
decided in December 2000 to approve the construction
implementation plan between Shin Aomori and Sapporo upon completion of the environmental assessment.
At last, concrete action was underway. The results of
the environmental assessment were announced in January
2002. A construction implementation plan centred on
roadbed was approved in April 2005 as the first phase of
construction between Shin Aomori and Shin-Hakodate,
and construction finally started. May 2010 marked the
approval for facilities related to opening the line, such as
track, machinery, structures, and electrical installations. Construction is ongoing towards completion in 2015. |
Figure 4: Image of Shared Track
Table 2: Length of Structures (Including Shared Track Sections)
Table 3: Length of Structures on Aomori Prefecture Side
Figure 5: Hokkaido Shinkansen Construction |
Overview of Section between Shin Aomori and Shin-Hakodate under Construction |
The most prominent feature of the section between Shin
Aomori and Shin-Hakodate where construction has started
is the shared section where the conventional Tsugaru-Kaikyo Line and shinkansen run on the same roadbed for
about 82 km. That shared track section has already been built to shinkansen specifications as the section between Naka-Oguni in Aomori Prefecture and Kikonai in Hokkaido, including the Seikan Tunnel, of the Tsugaru-Kaikyo Line. It opened in March 1985 and has been used as a conventional line.
The shared track section is being converted into three–rail track, and shinkansen, conventional line, and freight trains will run on the same roadbed. Land acquisition and
roadbed construction and other work is ongoing for a new 67-km section.
Structures on shared sections, such as the Seikan
Tunnel (approx. 54 km), are mostly complete and used by
conventional lines, but work to operate shinkansen, such as
conversion to three rails and stringing overhead catenary is
still ongoing. The shared track section on the same roadbed for shinkansen, conventional trains, and freight trains with
different systems, gauges, etc., is new operations territory
and development of supporting technologies, such as
three-rail digital ATC, three-rail turnouts, etc., is underway in earnest.
The lengths of structures, including the shared track
section, are shown in Figure 5.
Construction of the Shinshiro River bridge at the junction
with the Tohoku Shinkansen and all other civil engineering
construction, such as open sections and tunnels, started in
fiscal 2010. The 590-m Tatesawa Tunnel was broken through
in December 2008, making it the first completed tunnel of
the Hokkaido Shinkansen. The Tateshita Tunnel followed in December 2009.
The Tsugaru-Yomogita Tunnel (6190 m) runs through
mostly unconsolidated sands, and construction is expected
to be difficult. For safety, economy and work management,
it is being constructed using a cast-in-place tunnel support
system with a shield tunnel boring machine used successfully
for the Sambongihara Tunnel on the Tohoku Shinkansen. The
initial 162-m boring was completed in mid-February 2010, followed by full-scale tunnelling in March. |
Table 4: Lengths of Structure on Hokkaido Side
Photo: Tsugar-Yomogita Tunnel Shield Borer (JRTT)
Photo: Breakthrough in Oshima-Tobetsu Tunnel (JRTT)
Photo: Hakodate General Rolling Stock Yard Embankment (Vertical Drain) (JRTT) |
Overview of New Section in Hokkaido
(Kikonai to Shin-Hakodate) |
Figure 5 shows the new 38-km section between Kikonai and
Shin-Hakodate and the lengths of individual structures. The
Hakodate General Rolling Stock Yard (provisional name) is also in Hokkaido.
The new section on the Hokkaido side starts from the
junction with the shared track section near Kikonai. From
there, a two-platform, three-line, elevated station will be built
north of Kikonai Station on the JR Hokkaido Esashi Line,
through six long and short tunnels, across the Hakodate
plain to Shin-Hakodate Station, an over-the-tracks structure
at Oshima-ono Station on the JR Hokkaido Hakodate main
line. Shin-Hakodate Station will be the terminal station for the
time being, and is about 18 km from the city centre so the
convenience of changing at Shin-Hakodate for Sapporo still needs to be improved.
The Hakodate General Rolling Stock Yard will be about
1 km in the Aomori direction from Shin-Hakodate Station
between the Hakodate main line and shinkansen line.
It will have depot and maintenance facilities for Hokkaido Shinkansen rolling stock.
Time-consuming tunnel construction started in advance
of other work. Work started first on the longest 8-km Oshima-Tobetsu Tunnel in August 2005 and on all construction
sections including tunnels in March 2010.
The Oshima-Tobetsu Tunnel was the first on the Hokkaido
side to break through in August 2009, followed by the Koren Tunnel in December 2010.
Construction of open sections started in autumn 2009
with two sections including the Kikonai River bridge and
Ono River bridge. Construction, such as driving cast-inplace
piles, is proceeding on schedule. Preparation to start construction is underway in four sections at the Kikonai
roadbed, Mantaro roadbed, Iida viaduct, and Inasato
viaduct. Orders for all civil engineering construction will have
been placed this fiscal year.
Other construction involves reforming land at the
Hakodate General Rolling Stock Yard by bringing in
450,000 m3 of soil for an area of 360,000 m2. The geology
near the yard is soft ground, so subsidence is expected.
Construction started in February 2008 ahead of main line
open section construction. A test embankment was cut
in fiscal 2008 to determine the construction method, and
construction of the main embankment started in fiscal 2009 based on the results. |
Overview of Shared Track Section |
The 82-km conventional Tsugaru-Kaikyo Line to be shared with
the shinkansen requires both track and electrical construction.
Track construction involves adding a rail for the
shinkansen. The existing slab track already has rail
fastenings for the third rail. On ballasted sections, current
narrow-gauge sleepers will be replaced with sleepers for
three rails. Widening of embankments and other construction
for Yunosato signal box (provisional name) at the current
Shiriuchi Station was completed in November 2006. The
signal box will be used as a base for the aforementioned
track construction. Rail welding was underway there until
March 2010; welded rails have been transported from there
during the 4 hours of night when no trains are running for
full-scale rail laying in sections such as the Seikan Tunnel
since fiscal 2008.
Electrical construction for overhead catenary,
transformers and signalling is still needed. Catenary in the
Seikan Tunnel is heavy compound for shinkansen use, and
automatic tensioners are being installed at approximately
1.5-km intervals since 2008 to prepare for shinkansen. Shared sections outside the Seikan Tunnel originally had simple catenary for conventional trains but this is being
converted to simple catenary for shinkansen. The catenary
is also being realigned for use by both shinkansen and
conventional trains. The feed voltage is being changed from 20 to 25 kVac.
The current signalling system is ATC for conventional
lines, but a system for three rails will be developed and
feasibility tests have been conducted since fiscal 2007 on
a three-rail section between Shiriuchi Station and Kikonai
Station. These works must be done using a safe schedule
while conventional trains are running.
Many other items currently under consideration for
shinkansen operation include aseismic reinforcement of
viaducts, addition of tunnel portal hoods as countermeasures
to tunnel boom, cross-wind countermeasures for freight trains, and snow and noise pollution countermeasures. |
Figure 6: Image of Three-Rail Track Conversion
Figure 7: Three-Rail Track at Work
Photo: Three-Rail Track Laying (JRTT)
Photo: Surveying in Seikan Tunnel (JRTT)
Figure 8: Image of Overhead Contact Line Position Change (in Seikan Tunnel) |
Overview of Seikan Tunnel Survey and Function Maintenance/Renovation |
The Seikan Tunnel between Honshu and Hokkaido opened
in March 1985 is still the world’s longest undersea tunnel.
Facilities between Naka-Oguni and Kikonai including
the tunnel approaches are owned by JRTT, and trains of
JR Hokkaido and Japan Freight run on them. Tunnel
maintenance and renovation are extremely important for
reliably completing the Hokkaido Shinkansen and securing
safe operation.
Operations-related tunnel maintenance is performed by JR Hokkaido but the tunnel itself is maintained by JRTT.
JRTT understands the geologic and structural conditions
affecting the tunnel. It performs work such as analysis of
tunnel data, as well as comparison with construction data to
survey and confirm the tunnel soundness.
The Seikan Tunnel is made up of track, catenary, and
other equipment directly related to train operations, drainage
and other equipment related to tunnel maintenance, and
firefighting equipment related to disaster prevention in
long tunnels. These equipment function together to secure
safe transport in the Seikan Tunnel. They are in a very
difficult environment characterized by high humidity and
high airborne salinity and a 2008 survey showed some
equipment had degraded. As a result, renovation has being
ongoing since fiscal 2009, starting with equipment with
high priority in terms of safe transport. Renovation of items
such as structures and equipment is also needed to run
shinkansen trains, so plans are currently being made for
that too. For the tunnel as a whole, the following changes
and renovations need to be made.
• Earthquake disaster equipment
• Drainage equipment
• Fire detection equipment
• Firefighting equipment
• Power equipment
• Train control equipment
• Communications equipment
• Transformer equipment
• Others |
Figure 9: Plan and Side View of Seikan Tunnel
Table 5: Overview of Hokkaido Shinkansen between Shin-Hakodate and Sapporo |
Overview of Shin-Hakodate–Sapporo Section (construction not started) |
The 211-km Shin-Hakodate–Sapporo section of the
Hokkaido Shinkansen will start at Shin-Hakodate and pass
through Yakumo, Oshamambe, Kutchan, and Otaru before reaching Sapporo.
Although an application to approve the construction has
been made, it has yet to be approved. Surveys are continuing
so construction can start as soon as possible after approval
is received. Bore surveys for the Uchiura Tunnel, and station
surveys for Shin-Yakumo (provisional name), Oshamambe,
Kutchan, and Shin-Otaru stations (provisional name) were made in fiscal 2009.
A committee to study projected shinkansen line issues
headed by the Minister of Land, Infrastructure, Transport and Tourism started consideration of this section as well as sections of the Hokuriku Shinkansen and Kyushu Shinkansen (West Kyushu route).
The following five points are considered
basic conditions for starting construction: prospect of
stable funding; possibility of profitability; investment effect;
acceptance by JR Hokkaido as operator; acceptance by
local governments for managing parallel conventional lines.
In August 2010, this committee stated that more
detailed studies are needed where construction has not
yet started, including issues regarding sections currently
under construction. The following issues were brought up
regarding the Hokkaido Shinkansen: how operations will be
handled on the shared track section in the Seikan Tunnel;
how parallel conventional lines will be managed; a review of
maximum design speed (development plan). Extension of
the Hokkaido Shinkansen to Sapporo (start of construction)
will be possible by overcoming these issues and proactive
consideration and coordination by affected bodies will probably be very important. |
Conclusion |
Construction of the Hokkaido Shinkansen between Shin
Aomori and Shin-Hakodate started thanks to long years
of effort by those concerned and the enthusiasm of local
communities. 2010 marks the sixth year of construction.
Approval was received in May 2010 for facilities related to line
opening, marking the start of the final run up to completion
in fiscal 2015. Surveys between Shin-Hakodate and Sapporo
and of the Seikan Tunnel along with tunnel maintenance are
steadily going forward, and start of construction on sections
where construction has not yet started is desired.
Local communities have high hopes for the Hokkaido
Shinkansen in greatly contributing to the Tohoku and
Hokkaido economies. The Hokkaido Shinkansen is also expected to contribute to ideal usage of Japanese land as a whole, and issues delaying extension to Sapporo must be solved as soon as possible. Unwavering efforts, cooperation, and partnership by those involved are extremely important to achieve this goal.
JRTT must continue to work diligently on quality,
construction cost, and work schedule to assure on-time
completion to Shin-Hakodate. The technical skills fostered by this work are sure to pay off with an extension to Sapporo.
|